Don’s delighted to have me send this out to tell all interested parties that the strawbale house project has officially begun! (I’m not so sure how glad I am, yet…we’re hemorhaging $$$, and I’m afraid of bleeding out! No one can say WE aren’t helping the economy!) For your viewing pleasure, you will see the tentative schedule below. The good news is that there is now a rent-a-bathroom on the property for anyone who wishes to come for a visit and were afraid they were going to have to pee in a bucket! The bad news is the schedule below is already a day behind…oh well, Don can see holes where the footings go…so he’s a Hap, Hap, Happy Man!
Anyone seriously expecting a ‘wall raising party’ on the July 4th weekend can fahhh-get-about-it! We are going to try to get the builder to make some slight adjustments so that they get the roof on before the interior walls, so we can work on exterior walls at the same time…but that would put the wall raising, mid-July, at best!
We want to thank everyone who has shown the slightest bit of interest in this project…and apologize for being so self-involved for the past two years. We haven’t forgotten any of you…and I for one, appreciate your indulgence…
If you do not want to get updates about this farm project…I do not blame you…just let me know, and I will gladly take your name off the list.
If you want to visit, I believe there will be someone on or at the property from this day forward until winter…google 810 S. Meridian, Mason, Michigan for directions. If it’s VERY early in the morning, Don will be at the Wooden Nickel in Dansville having breakfast…he usually gets there before the cook does. If we’re not there, just look around (don’t fall in any holes!) someone will be back shortly. If you let us know you’re coming, we’ll have appropriate refreshments available.
| Excavating foundation |
6/1/2009 |
6/2/2009 |
| Footing inspection |
6/3/2009 |
6/4/2009 |
| Pour concrete footing and piers |
6/5/2009 |
6/9/2009 |
| Rough Plumbing |
6/10/2009 |
6/13/2009 |
| Rough Electrical |
6/11/2009 |
6/13/2009 |
| Rough Plumbing & Electrical inspections |
6/16/2009 |
6/17/2009 |
| install peastone |
6/18/2009 |
6/20/2009 |
| install foam and mesh |
6/22/2009 |
6/24/2009 |
| Radiant tubing |
6/23/2009 |
6/27/2009 |
| mechanical inspection |
6/30/2009 |
7/1/2009 |
| slab inspection |
6/30/2009 |
7/1/2009 |
| pour slab |
7/1/2009 |
7/3/2009 |
| post and beam framing |
7/6/2009 |
7/18/2009 |
| tromb walls |
7/6/2009 |
7/9/2009 |
| interior walls and shear walls |
7/15/2009 |
7/22/2009 |
| set trussess |
7/20/2009 |
7/25/2009 |
| roofing |
7/27/2009 |
8/1/2009 |